TGT full field development approved off Vietnam

Oil Gas Vietnam

Administrator
Thành viên BQT
An updated full field development plan (FFDP) for the Te Giac Trang (TGT) field, offshore southern Vietnam, has been approved by the country's government.

The FFDP was formally submitted to the relevant authorities in Q4 2016, says partner in the Hoang Long joint operating company, Soco. The plan comprises up to 18 additional wells on the field, with locations and additional support to be provided at a later date, and the addition of new processing equipment to be installed on the H1-well head platform.

a1.jpg

The processing equipment will be designed to handle 90,000 b/d of liquid with specific water handling capacity of up to 65,000 b/d of water.

Written by OE Staff​
 

Việc làm nổi bật

Top